MAHANKA/Indore/PROMOTER 360/SS NIRMAN PRIVATE LIMITED

SS NIRMAN PRIVATE LIMITEDCompany

Promoter Execution DossierFACT

Official regulatory footprint for SS NIRMAN PRIVATE LIMITED compiled from indexed MP RERA statutory filings.

Total Projects9
Absorption49.73%
COMPLETEDFACT
0
Officially declared completed
ONGOINGFACT
8
Under active execution
EXTENDEDFACT
1
Formal timeline extensions
OVERDUE / DELAYDERIVED
4
50% delay rate

Portfolio Economics & InventoryDERIVED

Aggregate scale reported across all RERA project filings

Total Registered Units746
Sold Units371
Remaining Units375
Estimated Construction Cost₹6,390.67 Lakh

All Projects in Portfolio (9)

Click any project to inspect the full 11-section statutory dossier

Project NameDistrictPlanning AreaStatusTotal UnitsSoldCompletion
SS INFINITUS - PHASE 15IndoreIndoreONGOING———
SS INFINITUS ZEUSIndoreIndoreONGOING——2030-10-31
SS INFINITUS ZEUSIndoreIndoreONGOING———
SS INFINITUS - PHASE 11IndoreIndoreONGOING63492026-04-23
SS INFINITUS - PHASE 12IndoreOtherONGOING43372026-04-23
SS INFINITUS - PHASE 11IndoreIndoreONGOING630—
SS INFINITUS PHASE-13IndoreIndoreONGOING29202026-04-23
SS INFINITUS - PHASE 9IndoreIndoreONGOING45452022-09-02
SS INFINITUS - PHASE 10, TOWER A AND TOWER BIndoreIndoreEXTENDED2402402024-09-03

Statutory Provenance & Objective Scope

This profile is an objective aggregation of public disclosures registered with the Real Estate Regulatory Authority (MP RERA). Mahanka does not compute subjective developer ratings, credit scores, or investment recommendations.

  • Inventory calculations represent statutory filings and may lag private sales by 1-2 quarters.
  • Completion status is taken directly from regulatory filings and does not constitute a physical structural audit.